Home Site Readiness

Getting the site ready

LEAP is preparing the land now before a specific project is identified so the HEOP is market-ready the moment opportunity comes.

$6.5M MEDC grant funding secured (2024)
9 Readiness studies & surveys completed
5 Readiness activities underway
Want the technical details? Jump to the due diligence tracker →

Preparing the land to compete

What “site readiness” means

LEAP has controlled the site since 2023 and is responsible for making sure the property is ready, competitive and positioned for the kind of investment Delhi Township’s Master Plan calls for.

At the direction of the Delhi Township Board, LEAP pursued and secured $6.5 million to advance through the Michigan Economic Development Corporation’s MI Sites Program. The funding pays for infrastructure improvements and the environmental, engineering and utility studies needed to bring the site to market safely and competitively.

How readiness lowers risk for a future user

Lower cost

Due diligence studies and infrastructure improvements reduce what a future user must spend before breaking ground.

Less uncertainty

Due diligence studies like environmental assessments, geotechnical surveys and title work answers key questions up front.

Faster timeline

Work completed now shortens the path from site selection to construction, and from operational launch to economic impact.

Readiness activities

Due diligence tracker

What’s been completed to date, and the on-site work you’ll see over the coming months. Summaries are linked here. Send us a message if intererested in the full reports.

Phase I Environmental Site AssessmentEnvironmentalOpen summary
Desktop Threatened & Endangered Species StudyEnvironmentalOpen summary
Desktop Cultural Resources ReportCulturalOpen Summary
Updated Wetland Delineation & EGLE WIP PermitEnvironmentalOpen summary
Traffic StudyEngineeringOpen summary
Geodynamic Evaluation ServicesEngineeringOpen summary
ALTA/NSPS Land Title SurveySurveyOpen summary
Preliminary Geotechnical SurveyEngineeringOpen summary
Community impact studiesCommunityIn progress
Phase II Environmental Site AssessmentEnvironmentalIn progress
Phase I Archaeological SurveyCulturalIn progress
Wetland Delineation & EGLE WIP PermitEnvironmentalOpen summary
Bat Habitat SurveyEnvironmentalIn progress
Ambient Noise StudyEngineeringIn progress
Entrance improvements: signage, grading and paved roadsInfrastructureIn progress
Engineering & cost studies for utilities and site layoutEngineeringIn progress

Process & timeline

How we got here and what’s next

From state identification in 2018 to today’s community engagement phase.

Before any proposal

A formal proposal from Lighthouse Sustainability would come forward only after community engagement and once the township’s data center moratorium allows.

  1. 2018

    MEDC identifies the site as a priority economic development opportunity.

  2. 2023

    LEAP secures the option via MEDC to control the property and begins work to advance readiness.

  3. 2024

    $6.5 million in state funding secured to advance readiness activities.

  4. 2025

    Environmental studies, pre-engineering and infrastructure planning, among others, underway.

  5. 2026

    LEAP selects Lighthouse Sustainability as its development partner following a competitive selection process.

  6. Now

    Community education and engagement, and continued site readiness work.

    We are here

On the ground